Windsor to Kedron (delivered with Airport Link)

Construction of the Northern Busway from Windsor to Kedron began in 2008 and is scheduled to be completed in 2012.

The three kilometre section of busway between Constitution Road, Windsor and Sadlier Street, Kedron is being delivered with Airport Link to maximise benefits and minimise local impacts during construction. The works around Federation Street, Windsor will also be delivered with Airport Link.

City North Infrastructure Pty Ltd (CNI) is managing the project on behalf of the State Government with BrisConnections selected as the preferred bidder to construct the project.

What will the busway between Windsor and Kedron look like?

The Northern Busway (Windsor to Kedron) includes:

The section of busway between the northern end of the Federation Street connection and Constitution Road will be delivered separately as demand increases.

View the latest concept design.

Project change report

A report detailing the changes to the Northern Busway (Windsor to Kedron) concept design (developed during planning) was developed following the evaluation period.

View the change report by chapter:

Alternatively you can view the full Northern Busway (Windsor to Kedron) change report here:

The Northern Busway (Windsor to Kedron) change report was made available for public comment between 31 May 2008 and 30 June 2008.

Submissions were received from businesses, government agencies and the public. View the submissions assessment and responses (PDF, 2.06MB).

Construction

For regular updates on construction impacts visit the BrisConnections site.

Get Abobe reader

Download Adobe Reader to display and print PDF files. This software is freely distributed by Adobe Systems Inc. While this department has taken every possible precaution with the creation of these files, they are downloaded and used at your own risk. Various tools to enable access to these files for people using screen readers can be found at www.adobe.com/accessibility.